
Monday, 21 June 2010
Friday, 19 March 2010
Refurbishment Progress 19th March 2010
Progress is going really well now on the hall refurbishment. All the demolition and cutting back is now complete, the roof has been stripped and we are well on our way putting things back. The external walls to the toilets and kitchen extensions are nearly complete and all the drainage has been replaced. We have also so much confidence in additonal grants coming in that we have instructed the contractor to make a start on the new store rooms as well. The photos tell the story. Roger has also had some money for landscaping and has planted trees on the bank.Wednesday, 3 March 2010
Progress to Date

This is my third report and will deal with what the builders have achieved to date. Since we started on 15th February all the demolition of the old lean too's is complete and we have started building the new foundations for the toilets and bar area. We are putting extra foundations in to carry another skin of external wall with lots of insulation.
Internally the old hall floor and stage have been removed. The floor we were hoping to save but it was too well fixed down and broke up as we lifted it so a new one has been ordered. The ceiling has gone and all the old fixtures and fittings. The stage has been taken out, about half of it was rotten with woodworm and this has been put out with the floor for firewood for the community.
Refurbishment - What Is Going On?
Hi this is my second report on the Village Hall refurbishment. In the excitement of getting the job started I didn't tell you what is happening so here goes.
We have been granted £300,000 by the Welsh Ministers and are expecting a further £90,000 from Biffaward and Rural Development Key Fund. This money together with some from Rudry District Council and hall funds will provide:-
New Toilets
New Kitchen
Large Side Conservatory Style extension to the hall overlooking the playing fields
New Roof
New Bar Area
Lots of New Storage.
New Ground Source Heat Pump and Ground Coils under the fields to get virtually free heat 24/7
New underfloor heating
New Hall Floor
New Windows and Doors
Lots of insulation to the external walls, floor and roof to keep all that precious heat in.
An overflow car park
New drainage
Lots of painting and decoration
New patio slabs
We have been granted £300,000 by the Welsh Ministers and are expecting a further £90,000 from Biffaward and Rural Development Key Fund. This money together with some from Rudry District Council and hall funds will provide:-
New Toilets
New Kitchen
Large Side Conservatory Style extension to the hall overlooking the playing fields
New Roof
New Bar Area
Lots of New Storage.
New Ground Source Heat Pump and Ground Coils under the fields to get virtually free heat 24/7
New underfloor heating
New Hall Floor
New Windows and Doors
Lots of insulation to the external walls, floor and roof to keep all that precious heat in.
An overflow car park
New drainage
Lots of painting and decoration
New patio slabs
Friday, 26 February 2010
Refurbishment Progress Report

Progress Report Dated 17th February 2010
The Village Hall Refurbishment Project has started. Contractor Indigo 360 started yesterday. I am Mike the Project Manager. I will be giving regular updates and photos here to keep you informed on progress the first update follows.
The Village Hall Refurbishment Project has started. Contractor Indigo 360 started yesterday. I am Mike the Project Manager. I will be giving regular updates and photos here to keep you informed on progress the first update follows.
Progress
Indigo have completed site establishment and stripped most of the external areas. They have about half of the floor up and the stage has been stripped out. They have carried out a reduced level dig of the Phase 5 area which will be used to dispose of excavated materials, this is a win win as we don’t pay for cart away and we get Ph 5 prepared also.
The project is compliant with the CDM Regulations. The Welfare facilities comply and the contractor has a comprehensive construction phase health and safety plan on site.
The stage had two main parts, a specialist modular frame and infill joists and decking. The in filled areas are full of woodworm and need to be disposed of. This will mean new materials have to be purchased when the stage is rebuilt.
The hall floor will not lift without damage and therefore we will have to purchase a new floor.
There is now a large pile of timber on site for those with wood burning stoves.
The new floor will look fantastic.
Subscribe to:
Posts (Atom)







