Wednesday, 3 March 2010

Progress to Date











This is my third report and will deal with what the builders have achieved to date. Since we started on 15th February all the demolition of the old lean too's is complete and we have started building the new foundations for the toilets and bar area. We are putting extra foundations in to carry another skin of external wall with lots of insulation.








Internally the old hall floor and stage have been removed. The floor we were hoping to save but it was too well fixed down and broke up as we lifted it so a new one has been ordered. The ceiling has gone and all the old fixtures and fittings. The stage has been taken out, about half of it was rotten with woodworm and this has been put out with the floor for firewood for the community.








The next week will see the rest of the roof taking off ready for a new one, the drainage going in and the new walls being built.